Durations of O&M Jack-up Interventions
Sea Impact insight: How does the WTG platform impact the duration of O&M jack-up interventions?
The MHI Vestas Offshore Wind V112-3.0/3.3 platform has had the shortest median O&M jack-up intervention duration of just 0.82 days while the Senvion 5.0/6.2M platform has been the slowest with a median duration of 3.94 days.
Generally, the O&M jack-up interventions have been significantly shorter at smaller WTG platforms, compared to larger ones.
Among the other factors that affect the duration of O&M jack-up interventions are:
– the type of component that was replaced
– site conditions (e.g. weather and water depth)
– the vessel that was utilized