Hornsea 2 Installation & Commissioning Completed

Last week, the world’s largest wind farm Ørsted’s Hornsea 2 entered full operation, following the completion of the Hornsea 2 installation earlier this year (Source).

Today, we provide you with an insight into the Hornsea 2 installation campaign – taken from our market intelligence platform.

Try the dashboard right here (allow cookies to make the dashboard appear). Click the full-screen mode in the bottom right corner for the best experience.

The 165 Siemens Gamesa SG 8.0-167 DD turbines were installed by DEME’s Sea Installer and Sea Challenger in 230 days. The average on-site duration for turbine installation was 1.8 days per turbine. The monopile foundations were installed by DEME’s Innovation and Cadeler’s Wind Osprey.

Key use cases of our project-level dashboards:

  • Select the best logistical setup for your installation
  • Improve the accuracy of your installation budget
  • Improve the accuracy of your installation schedule
  • Benchmarks your contractors’ performance

Contact our Project Manager, Lars-André Bugge Tobaben, to hear more about our market intelligence platform.

Share the dashboard with a colleague — and comment below what insight you would like to see next time!

# SeaImpact # OffshoreWind # Hornsea 2 Installation