In January, the turbine commissioning was completed at RWE’s Triton Knoll offshore wind farm in the United Kingdom.

Today, we provide you with an insight into this installation campaign – taken from our market intelligence platform.

Try the dashboard right here (allow cookies to make the dashboard appear). Click the full-screen mode in the bottom right corner for the best experience.

The 90 Vestas V164-9.5 turbines were installed by Cadeler’s Wind Osprey in 237 days. The campaign consisted of 19 cycles of 5 turbines each. The average cycle duration was 12.3 days, and the average on-site duration for turbine installation was 2.1 days per turbine.

Key use cases of our project-level dashboards:

  • Select the best logistical setup for your installation
  • Improve the accuracy of your installation budget
  • Improve the accuracy of your installation schedule
  • Benchmarks your contractors’ performance

Contact our Project Manager, Lars-André Bugge Tobaben, to hear more about our market intelligence platform.

Share the dashboard with a colleague — and comment below what insight you would like to see next time!

#SeaImpact #OffshoreWind #TritonKnoll