Last Sunday, the turbine installation was completed at Vattenfall’s Kriegers Flak offshore wind farm in Denmark.

Today, we provide you with an insight into this installation campaign – taken from our market intelligence platform.

Try the dashboard right here. Click the full-screen mode in the bottom right corner for the best experience.

The 72 Siemens Gamesa 8.0-167 DD turbines were installed by Jan de Nul’s Vole Au Vent in 130 days. The campaign consisted of 18 cycles of 4 turbines each. The average cycle duration was 7.2 days, and the average on-site duration for turbine installation was 1.3 days per turbine.

Click the link above to try the dashboard and see many more KPIs and insights.

Key use cases of our project-level dashboards:

• Select the best logistical setup for your installation

• Improve the accuracy of your installation budget

• Improve the accuracy of your installation schedule

• Benchmarks your contractors’ performance

Contact our Project Manager, Lars-André Bugge Tobaben, for more installation cycle breakdowns and offshore wind insights.