Installation Cycles at Deutsche Bucht

Our weekly #SeaImpact update: Did you know that it took only 8 installation cycles to install the 31 turbines at Deutsche Bucht?

The turbine installation took 89 days of which 78% were spent on site, 13% in the Port of Esbjerg and 9% in transit.

Click around below to gain more insights into the turbine installation at Deutsche Bucht.